Karachi, September 25, 2020 (PPI-OT): K-Electric (KE) said on Friday that it continues to be challenged by low gas pressure from the Sui southern Gas Company (SSGC). The quantity of the required gas remains available, but decreased pressure leads to a decline of 250MW to 300MW electricity supply at a time when demand is high, it said in a statement.

The company said that because of low gas pressure, KE’s power plants at Korangi and SITE are not able to operate at their optimum capacity despite remaining fully available. To resolve this issue, KE has requested to purchase re-liquefied natural gas (RLNG) if made available at required gas pressure to meet short term requirements and is awaiting confirmation on the same. At the same time the power utility has also requested the federal government to increase supply from the National Grid till 800 MW from existing NKI and Jamshoro interconnections.

It said: KE’s furnace-oil fired power plants are fully functional at this time. KE has expressed concerns that the continued curtailment of gas pressure may lead to socio-economic challenges due to increase in load shedding hours across all consumer segments including industrial zones. At the same time the power utility is grateful to the federal ministry and other stakeholders for their support during this difficult time.”

For more information, contact:
Media and PR Department,
K-Electric
KE House, 39-B, Sunset Boulevard, Phase-II,
Defence Housing Authority, Karachi, Pakistan
Tel: +92-21-32637133, +92-21-38709132
Cell: +92-300-2281183, +92-346-8223641
Website: https://www.ke.com.pk