Progress review meeting on Islamabad Metro Bus project – Peshawar Morr to New Islamabad International Airport

Islamabad, October 06, 2021 (PPI-OT):Chairman CDA Mr. Amer Ali Ahmed, in a meeting attended by CDA officers and consultants of the project, reviewed progress on Islamabad Metro Bus project from Peshawar Mor to New Islamabad International Airport.

It was observed during the meeting that there were some missing aspects in project’s scope of work initiated earlier. Therefore, a separate PC-1 was prepared by CDA in consultation with experts to include required facilities such as intelligent Transportation system including automated fare collection, security surveillance system, Bus scheduling system, vehicular location system and command and control system among others.

The consultants briefed about the facilities to be provided to the commuters at each bus station to facilitate them which include walk through gates, security cameras, Wi-Fi, real time passenger information display, public announcement system and validators.

A detailed lay out plan of the bus depot was also presented in the meeting. Bus depot contained separate areas for maintenance workshop, service area, resting area for drivers, admin block, parking bays, command and control centre and offices.

It was decided that Bus depot will not only cater for the requirements of the Metro Bus service project but will also fulfil similar needs of the Islambad Bus service project. One depot will provide a consolidated and comprehensive cost effective solution. This will bring savings to the exchequer also.

A day care center to facilitate female staff with children, small barrack for guards providing security to the facility and provision of special ramps, rails and separate rest rooms for differently abled persons were added in the facility and lay out plan was approved in principle in the meeting.

Chairman CDA directed the Project Director and consultants of the project to ensure that procurement of buses is completed within 4 months period in order to extend this facility to the citizens of the capital in shortest possible time.

As for infrastructure, instructions were issued that pre-engineered structures and steel frame construction to be followed so that completion of depot and control room is done in six months. The control room will not only cater for the airport project but also fulfill requirements of the Islamabad bus service and smart traffic management systems. Collective housing of the facilities will bring about savings. It is pertinent to mention that tenders for procurement of buses have already been floated and now the tenders for construction of depot and systems will also be floated to meet the timelines.

For more information, contact:
Public Relations Directorate
Capital Development Authority (CDA)
Main Office, G-7/4, Islamabad
Tel: +92-51-9252614
Email: getreply@cda.gov.pk
Website: www.cda.gov.pk