KARACHI: Sindh Chief Minister Syed Murad Ali Shah keeping in view the water requirement of the city has decided to install two new Seawater Desalination plants, each one of 5 MGD, and to acquire a seawater desalination plant abandoned at KANUPP. “This will help to provide drinking water to the people living in old areas of the city to the DHA.”

This he said on Sunday while presiding over a meeting to review the status of some important projects of the city here at the Cm House. The meeting was attended by Minister Information Sharjeel Memon, Minister Local Govt Nasir Shah, Administrator KMC Murtaza Wahab, Chief Secretary Sohail Rajput, Chairman P and D Hassan Naqvi, Commissioner Karachi Iqbal Memon, Secretary LG Najam Shah and Special Secretary to CM Raheem Shaikh and other concerned officers.

5 MGD Seawater Desalination Project: The meeting was told that Karachi was the city of 20 million souls and its water requirement stood at 12,00 MGD against which 655 MGD was being provided showing a shortfall of 535 MD.

Minister Local Govt Nasir Shah said that KWSB has prepared a scheme to set up a Seawater Desalination Plant (SWDSP) of five MGD capacity to supply water to the users in district South. Three locations for installation of desalination plants- Ibrahim Hyderi, Ayesha Masjid DHA-VII and Seaview at village restaurant were proposed. The CM approved Ibrahim Hyderi at Korangi Creek which is one and half kilometers away from Dhari Island.

The intake from this location would supply water to the Ghazi Pumping Station via Coast Guard Chowrangi where another pumping facility is available as a backup in case of a failure or other emergent circumstances at Ghazi Pumping Station.

The chief minister directed the local government department to install another 5 MGD desalination plant near Lyari so that Lyari could be provided water from there. He also directed the local government minister to talk to a private firm which had installed a 1.2 MGD desalination plant to provide water to KANUPP. The KANUPP has installed its own plant therefore that plant was abandoned and could be used to provide water to the city.

Minister local said that he had held a meeting with the concerned private firm and they were ready to enhance SWDSP’s capacity. At this the CM directed him to do it at the earliest.

Korangi Causeway bridge: The chief minister approved a one- km bridge on Korangi Causeway Bridge and 1 km approaching from while going from the DHA and 200 km after the causeway.

Mr Shah set the timeline of the bridge and directed the local government department to complete detailed design by August 31, 2022, bidders post qualification (international tender) by September 30, bid evaluation and award of work by October 31, and start of the construction by November 1, 2022.

It may be noted that earlier, the bridge was proposed to be constructed under PPP mode but now it would be an ADP scheme of Rs5 billion.

65 MGD project: The CM was told that the additional 65 MGD water would be brought through Haleji Lake to Pipri via an integrated system of Canal, Conduit, Pipeline, Pumping Station and other necessary ancillary works. Minister Local govt Nasir Shah said that presently this balance 65 MGD water would be drawn through Kalri Gujjo Canal and transmitted by gravity to the proposed Gharo Pumping Station from where water would be pumped to High point of Forebay of KWSB where new Forebay Chamber would be constructed and from Forebay water would be gravitated to Pipri filter Plant. The works proposed to be taken (General works) include four packages.

Package-1: Construction of RCC lined Canal and RCC Conduits from Haleji Lake to Gharo Pumping station, including construction of intake structure at Haleji Lake and Keenjhar Gujjo Canal.

Package-2: Construction of new 65 MGD Pumping Station, including Mechanical and Electrical works at Gharo.

Package-3: Laying of 72-inch dia MS Rising Main from new proposed Pumping Station at Gharo to Forebay, including construction of new Forebay Chamber at high point.

Package-4: Laying of RCC Conduit Gravity Main from Forebay Chamber to Pipri Filter Plant.

The chief minister directed the local govt department to restart the work on the packages one to three so th